Good afternoon, Holiday Condo and Happy Monday! 


I trust everyone had a great weekend. The board and management team are pleased to provide the owners with a summary of our current projects.


Fiber Optic 

Crews are expected to be on site to address any remaining concrete replacement and

settlement issues. We hope to have internet service live sometime in August, however,

while the park may be ready, there is fiber yet to be installed along San Carlos Blvd. We

will keep you informed about upcoming informational meetings with our account

representative.


Indoor Pool

Flooring is complete with minor punch list items remaining. There is some minor

painting remaining in the men’s and women’s shower rooms. The new sauna unit has

arrived. Additionally, new benches in the sauna will be installed. A grand opening will

be scheduled in the very near future.


Governing Documents

The revised HC Condominium Governing Documents have been distributed to the owners via the HC Website and email.  Three copies of the current and proposed documents can be found at the South Hall. Two owner’s workshops have been held at the South Hall and via Zoom.  Weekly blogs are posted to the HC Website, and email, where owners can go to see factual comparisons between the existing and proposed documents.  We are committed to providing our ownership with the most accurate information enabling you to make your decision.  Again, these are DRAFT documents, and we welcome all constructive input and questions.



Water Valve Replacement

Last week, Atlas Drainworx was on site and completed excavation of six additional

valve locations. Due to unforeseen conditions no valves were replaced this past week.

Atlas Drainworx will return to our park on Tuesday, Wednesday, and Thursday, with our

next scheduled water shut down scheduled for Wednesday July 29th at 9AM. We know

this is extremely frustrating and disruptive; however, we will continue our efforts until the

faulty valves have been replaced.


Additionally, we recommend you change the aerators on your sinks and showers to

ensure there is no sediment reducing your water flow.



Tennis Courts

Resurfacing of Tennis / Pickleball courts is scheduled to begin August 10th


Street improvements

Street improvements this year will likely be limited to sealing of asphalt. There will also

be repairs made around some of the drain boxes. This work is scheduled to begin

sometime in late September or October


“Please check the Holiday Condo Website for important updates and information.  The Board of Directors and Park Management does not post park business on Happenings, Connections, and Advocates FB pages.”


Lastly, I want to thank Pete Lallo and the management team for all they do. It takes a huge effort to keep the park operating, regardless of the number of people on site.   


Thank you,


Kevin Stevens, President

 
 
 